Pelton Horizontal – 3.2 MW – Nova Caledónia

Flashback with pics of an horizontal Pelton Turbine of 3.2 MW installed in an hydroelectrical plant in New Caledonia and commissioned early 2021.

Scope of supply:
– Inlet Valve
– Turbine
– Generator
– HPU

Net head : 498.8 m
Discharge : 0.71 m³/s
Turbine rated speed : 1000 rpm
Pelton diameter : Ø 919 mm

3D Design

Manufacturing in our french workshop

Assembly of the injectors and runner
 
Installation and commissioning of the plant

View of the ocean from the site